Cambridge CT Paving Project – Aug 9th to Aug 13th

The Cambridge CT paving project will begin this Friday, August 9th and – weather permitting – run through Tuesday, August 13th. Paving activities will take place from 7:00 am to 5:00 pm on weekdays during which time Cambridge CT will be inaccessible. *Work will not take place on the weekend.

The street will re-open for access at the end of each day and the paving contractor Schlouch, Inc will work with property owners if they need to get in or out of their driveways.

Cambridge CT residents have temporary township permission to park their vehicles on the outer Hawthorne Drive loop and may also utilize the clubhouse parking lot for the duration of the project. The township has also notified first responders of the project timeline.

Residents who normally use Cambridge CT as a shortcut to the pool, etc should take an alternate route for the duration of the project.

A big thanks to Denise and Dave of our Paving Committee for their assistance with this project.