Update – Cambridge CT Paving Project – Aug 12th to Aug 14th

REVISED PAVING SCHEDULE

The Cambridge CT paving project will begin this upcoming Monday, August 12th and – weather permitting – run through Wednesday, August 14th. Daily paving activities will take place from 7:00 am to 5:00 pm during which time Cambridge CT will be inaccessible.

The street will re-open for access at the end of each day and the paving contractor Schlouch, Inc will work with property owners if they need to get in or out of their driveways.

Cambridge CT residents have temporary township permission to park their vehicles on the outer Hawthorne Drive loop and may also utilize the clubhouse parking lot for the duration of the project. The township has also notified first-responders of the project timeline.

Residents who normally use Cambridge CT as a shortcut to the pool, etc should take an alternate route for the duration of the project.

A big thanks to Denise and Dave of our Paving Committee for their assistance with this project.