Hawthorne Drive Project Updates

Here are updates on the Township’s Hawthorne Drive Project.

The Culbertson Run (Hawthorne Drive) Stormwater Improvement Project was placed out for bid with bids due on May 13th, 2020 – it will be a 4 month (120-day) project

    1. Subsurface basins will be done in phases so that the work does not block resident access to any of our streets
    2. Funding from 3 sources – Current cost = $804,672.00
      1. Existing 2018 Growning Greener Grant – $246,021
      2. Capital – $312,119
      3. Liquid Fuels Fund $246,532
    3. Property “rights to entry” requested from all homeowners were not 100% fulfilled so there will be 6″-to-12″ tall railroad tie retaining walls, instead of grading/swales, along two homeowner properties
    4. The bid includes grinding and removing 74 tree stumps
    5. Relevant pages from the overall 111 page March 27th township meeting agenda packet may be found here
    6. The project was discussed in the Township’s March meeting/conference call – https://www.youtube.com/watch?v=21osV0LbpNg