Canterbury CT Paving Project – Week of July 31

The HOA Board has awarded a Canterbury CT repair & resurfacing bid to JENA Asphalt Solutions. The work will begin the week of Monday July 31.

Anticipated timeline:

  • Monday July 31 – stage equipment, residents relocate vehicles to Hawthorne Drive (outer-loop only)
  • Tuesday Aug 1 – mill & repair – Road closes. Trash/Recycling service will be accommodated
  • Wednesday Aug 2 – pave/overlay
  • Thursday Aug 3Road reopens

Residents will receive more specific instructions via flyers delivered to their households before, during, and after the project.