Paving Project – Chapel & Brookfield Courts

Chapel and Brookfield Courts Paving Project – Week of June 29, 2026

Dear Residents,

The HOA Board is pleased to announce that JENA Asphalt Solutions has been awarded the bid for the repair and resurfacing of Chapel and Brookfield Courts. This important project will begin the week of Monday, June 29, 2026.

Work will commence daily at 7:30 AM. Please review the anticipated timelines and parking restrictions below:


CHAPEL COURT – Anticipated Timeline:

  • Monday, June 29 Mill & Repair:
    • Road Status: Limited access during the day.
    • Vehicles/Parking: Vehicles may still use the street during the day, but must park on the outer loop of Hawthorne Drive overnight. Vehicles will not be able to exit or enter Chapel Court on Tuesday,  June 30. 
  • Tuesday, June 30 Base Repairs & Paving:
    • Road Status: CLOSED ALL DAY for paving.
    • Parking Restrictions: No parking or vehicle traffic permitted on Chapel Court until Wednesday, July 1.
    • Trash/Recycling Service: Waste collection services will NOT be accommodated on Tuesday. 
  • Wednesday, July 1 Project Completion:
    • Road Status: The road will reopen.
    • Cones: Cones will be removed once the road is fully reopened.
    • Trash/Recycling Service: Place trash cans and recycling cans at the curb Wednesday after JENA Asphalt Solutions is finished. Do not place them on the new road, keep them at the curb on driveways or lawn.
  • Thursday, July 2 Trash/Recycling Service:
    • Trash/Recycling Service: Waste collection services will be prior to noon on Thursday.

BROOKFIELD COURT – Anticipated Timeline:

  • Wednesday, July 1 Mill, Repair, & Drain Repair:
    • Road Status: Limited access during the day.
    • Vehicles/Parking: Vehicles may still use the street during the day, but must park on the outer loop of  Hawthorne Drive overnight. Vehicles will not be able to exit or enter Brookfield Court on Thursday,  July 2.  
  • Thursday, July 2 Base Repairs & Paving:
    • Road Status: CLOSED ALL DAY for paving.
    • Parking Restrictions: No parking or vehicle traffic permitted on Brookfield Court until Friday, July 3.
  • Friday, July 3 Project Completion:
    • Road Status: The road will reopen.
    • Cones: Cones will be removed once the road is fully reopened.

We understand that this project will cause some temporary inconvenience, and we appreciate your cooperation and patience as we work to improve our community’s infrastructure. Please plan ahead for vehicle relocation and road closures. Remember to park on the outer loop of Hawthorne Drive. A blanket request was opened with the township.

If you have any urgent questions during the project, please contact Trident Property Management at hha@tridentpropmgt.com

Thank you,

HHA Board